Engineering, Procurement of Materials and Equipment for Permanent Installation, Training, Construction and Commissioning of 2 Transmission Line with 400 kV voltage and a length of 424.2 Km-C (LT Juile – Cerro de Oro 400 kV-154.28 Km-C And LT La Ventosa – Juile 400 kV 270.6 Km-C), and 3 Substations with 400, 230 and 115 kV ballasts with a capacity of 2,125 MVA, 75 MVAr and 8 Feeder (SE Cerro de Oro 400 kV, SE Juile + MVAr 400 kV and SE Ventosa Bcos.1, 2 and 3 400/230/115 kV). The holder of the Contract with CFE was constituted by the Companies. ISOLUX, ELÉCTRICAS / EDEMTEC, PIDIRELYS (Eléctricas de Medellín / Edemtec has a 21.02% stake in the Project).
Start Date: 12-sep-08
Final Date: 01-sep-10