ELECTRICAL SUBSTATION. CONTRACT NO. PIF-010/2014 PROJECT "243 SE 1322 DISTRIBUTION CENTER 5A PHASE"

Construction and Installation of 5 (five) Transmission Lines with 115 and 23 kV voltages and 175.24 km-C length of high-voltage airline, 2.67 km-C of high-voltage underground line, 3.70 km-C of airline Of medium voltage and 5.76 km-C of medium voltage underground line and 5 (five) substations with voltages of 115 and 23 kV, with capacity of 80 MVA, 4.8 MVAr of compensation and 29 feeders, to be located in the state of Jalisco , Of the United Mexican States “.

Start Date: 22-may-14
Final Date: 12-dec-15

ELECTRICAL SUBSTATION. CONTRACT NO. PIF-014/2010 "170 LT TRANSMISSION NETWORK ASSOCIATED WITH THE CHIEF CHAMBER"

Construction and installation of two (2) transmission lines with a voltage of 400 kV and a total length of 220.1 km-C and two (two) substations with a voltage of 400 kV and 116.9 MVAr of inductive type compensation and 4 (Four) feeders, to be located in the state of Jalisco, United States of Mexico. The holder of the Contract with CFE was constituted by Cias.IBERDROLA, ELÉCTRICAS and EDEMTEC, SIMENES in which Electricidade de Medellín / Edemtec has a 41.10% stake in the Project.

Start Date: 05-jul-10
Final Date: 15-may-12