ELECTRICAL SUBSTATION. CONTRACT NO. RRNE-101010

Engineering, Training, Procurement, Supply, Construction Civil and Electromechanical Works, Assembly, Testing and Commissioning of 2 Works of Transmission Lines with voltages of 400 kV and a length of 443.9 Km-C (TL Saltillo CC – May Day 400 KV, 2C, 223.3 Km-C ACSR / AS 1113 and LT First of May – Cañada 400 kV, 2C, 220.6 Km-C ACSR / AS 1113), and 3 Works of Substations with voltages of 400 kV with a capacity of 300 MVAr And 4 Feeders (SE Saltillo CC + MVAr, SE First of May + MVAr and SE Cañada), located in the States of Aguascalientes, Coahuila, San Luis Potosí and Zacatecas.

Start Date: 03-jan-11
Final Date: 30-aug-11