Construction and installation of 3 (three) Substations with a total capacity of 48 MVAr of compensation, with 4 (four) feeders in 230 and 115 kV; 2 (two) Transmission Lines with 230 kV voltage with a total length of 367.4 km-C that will be located in the States of Campeche and Quintana Roo, United Mexican States.
Start Date: 02-jul-15
Final Date: 21-jan-17