México – Guerrero

"LT 303 IXTAPA – PIE DE LA CUESTA" PROJECT. CONTRACT PIF-010/99

Engineering, Supply, Construction, Training and Commissioning of the Following Works, Located in the State of Guerrero:
►LT Ixtapa – Foot Of The Slope. 400 Kv, 207 Km-L; Conductor Cable: Acsr / As 1113, 2 Wire / Phase; Guard Cable: 2 Aas 7 No. 8 Awg.
►LT Foot Of The Slope Entq. Mezcala – El Quemado. 230 Kv, 22 Km-L, 66 Km-C; Conductor Cable: Acsr / As 1113, 1 Wire / Phase; Cable of Guarda: 1 Aas 7no. 8 Awg + 1 Opgw 36 Fibers.
►LT El Quemado Entq Mezcala – Los Amates. 230 Kv, 5.00 Km-L, 10.00 Km-
C; Conductor Cable: Acsr / As 1113, 1 Wire / Phase; Cable of Guarda: 1 Aas 7no. 8 Awg + 1 Opgw 36 Fibers.

Start Date: 01-sep-09
Final Date: 01-sep-11

"68 LT TRANSMISSION NETWORK ASSOCIATED WITH THE PACIFIC" PROJECT. CONTRACT No. PIF-010/2008

Engineering, Procurement, Supply, Construction, Training and Startup of 2 LT’s of 400 Kv and a Total Length of 282.3 Km-C and 3 SE’s with Voltages of 230 Kv, with a Capacity of 21 Mvar and 9 Feeders, 4 New And 5 Equivalents For Increased Interrupting Capacity, Located In Edo. Of Guerrero Of The United Mexican States.
►LT Ixtapa Pot. – Foot Of The Cuesta Pot. 400 Kv. Initial Operation At 230 Kv, 2c, Existing Self-Support Towers, 207.70 Km-C; Conductor Cable: Acsr / As 1113, Two Conductors Per Phase. Laying Of The Second Circuit. Includes The Substitution Of 207.70 Km Of Cgfo And The Retreat Of 3 Structures.
►LT Lázaro Cárdenas Pot. – Ixtapa Pot. 400 Kv Initial Operation A 230 Kv, 2c, Self-supporting Towers, 74.60 Km-L, 74.6 Km-C; Conductor Cable: Acsr 1113, Two Conductors Per Phase; Cords of Guard: Opgw Of 36 Fibas + Aas 7no. 8 Awg.
►SE Lázaro Cárdenas Pot. 15 50 KA Switches Of Interrupting Capacity And Serial Equipment. Includes 230 Kv Bar Recalibration With Current Configuration.
►SE Foot Of The Cuesta Pot. 1a 230 Kv (3 X 7 Mvar) LT Ixtapa Pot.
►SE Ixtapa Pot. 1a 230 Kv LT Lázaro Cárdenas, 1a 230 Kv LT Pie De La Cuesta (C2).

Start Date: 12-may-08
Final Date: 02-jan-08

P1902 PROJECT. CONTRACT P1902

Engineering, Supply of Materials and Equipment for Permanent Installation, Training, Construction and Commissioning of 2 Transmission Line with 400 kV voltage and a length of 282.3 Km-C (LT Lázaro Cardenas Pot -Ixtapa Pot 400 kV-74.6 Km- C and LT Ixtapa Pot – Piede lla Cuesta 400 kV-207.7 Km-C), and 3 Substations with 230 kV voltage with a capacity of 21 MVAr and 9 Feeders (SE Lázaro Cardenas Pot, SE Foot of the Cuesta Pot + MVAr y SE Ixtapa Pot). The holder of the Contract with CFE was constituted by the Companies. ABENGOA, SIEMENS AND ELÉCTRICAS / EDEMTEC (Electricity of Medellín / Edemtec has a 29.92% stake in the Project).